Migrating from Non-Integrated CCP to Integrated CCP
To migrate the non-integrated IntelePeer location into an integrated IntelePeer location, follow these steps:
1 |
Log in to the Control Hub, go to Calling and then click PSTN. A migration banner displays with the locations to migrate when there are locations which need to be migrated from a non-integrated intelepeer location to an integrated intelepeer location.
|
2 |
Click Begin Migration to start the migration process. The migration wizard is displayed. Make sure there are no errors displayed in any of the sections within the Number Audit Report tab.
|
3 |
Click Analyze and move forward to navigate to the next step of the migration process. The Confirmation tab is displayed. A list of non-integrated intelepeer location to migrate displays.
|
4 |
Check the I have read and accept to start Migration checkbox to enable the migration. |
5 |
Click Start Migration to start the migration process. The Contract Information tab displays with the fields pre-populated.
If the fields do not pre-populate, fill in the details. |
6 |
Click Next to navigate to the location migration tab. The Location Migration tab is displayed. The list of locations to migrate displays.
|
7 |
Select each location you want to migrate and click Validate Address to verify the location details. If you can’t validate the address, a suggested address displays. Click Apply, to apply the location details. |
8 |
Click Migrate Now to migrate to the selected locations. Successful migration of a non-integrated intelepeer location to an integrated intelepeer location is complete.
|
9 |
Click Close to close the migration wizard and navigate to the PSTN tab. The migration banner disappears on successful migration of all non-integrated intelepeer location to an integrated intelepeer location.
|